New Entrance Clearance, Topsoil Stripping, Hardcore
This phase commenced: 15 August 2011
This phase completed: 5 September 2011
This phase was contracted to: ourselves
Includes: Opening the new entrance, stripping topsoil, laying hardcore, logging, demolishing old garage, removing part of existing hedge, rolling hardcore flat.