Foundations
This phase commenced: 23 September 2011
This phase completed: 02 November 2011
This phase was contracted to: East Cornwall Construction
This phase completed: 02 November 2011
This phase was contracted to: East Cornwall Construction
Includes: Setting Out, Digging Trenches, Pouring Concrete, Laying Trenchblocks, Initial Drainage, Damp-proof course, Blockwork, Concrete Beam Laying, Blocks into beams, Coursing Blocks, Slurry and finishing with a hardcore gravel in preparation for scaffolding.